Background
Max Aicher GmbH & Co.KG operates in the business areas of Steel & Production, Environment & Recycling, Real Estate & Projects, and Construction & Engineering.
MAX AICHER plans to set up a production facility for graphite electrodes (for electric arc furnaces). A technical center with a graphite green production facility is to be built at the LSW Lech-Stahlwerke GmbH site in Meitingen and later expanded in a modular fashion.
MAX AICHER commissioned Projektingenieure (PI) with the design and implementation of the new technical center.
Results
- New production hall (technical centre) for the green production of graphite electrodes, including laboratory, offices and social rooms.
- Dismantling of old facilities in Grießheim and reconstruction of the refurbished facilities in Meitingen.
- Production subdivided according to process steps and ATEX areas.
- New filter system.
- Implementation of the highest requirements for occupational safety, environmental protection and energy efficiency.
PI services
Factory planning, process planning
Concept design
analogous to VDI 5200, phases 2 to 3
- Capacity requirements and material flows simulated
- Production areas defined according to process steps and ATEX requirements
- Mixing
- Heating
- Crushing
- Mould filling, pressing, demoulding
- Cooling
- Sending for graphitisation
- Logistics concept (material flow, staging areas, conveyor systems) created
- Layout start and modular extensions created
- Resources (personnel, equipment, buildings, infrastructure) dimensioned
- Investments determined
- Master plan for implementation created
Detailing
analogous to VDI 5200, phases 4 and 5
- Detailed manufacturing segments
- Machine layout plan created
- Diagram for process flows and media supply created
- Piping and instrumentation diagram (P&ID) created
- Equipment list created
- Plant technology (including filter technology) specified
- Relocation and overhaul of existing facilities specified, put out to tender and prepared for awarding contracts.
- Plant engineering put out to tender, bids obtained and prepared for awarding contracts.
- Buildings and technical systems (hall ventilation, exhaust air purification, etc.) specified.
- Approval documents prepared.
- Budget and schedule drawn up, project controlling established.
Implementation
analogous to VDI 5200, phases 6 and 7
- Managed supplier performance, organized acceptance procedures
- Installation/integration of newly procured equipment
- Relocation/integration of existing systems
- Budget (investments) tracked
Topics
Factory planning: Value stream, production segments, material flow, layout, scalability, step-by-step expansion, facilities/infrastructure/buildings, cleanliness, environmental protection
Process planning: Process engineering, plant engineering, simulation of capacity requirements, automation, interlinking, energy efficiency, IT, control technology, machine and process data acquisition, Industry 4.0
Logistics planning: Conveyor technology: Warehouse technology/transport technology, order picking technology, fire protection
Trades
Gating, mixing, heating, crushing, mold filling, pressing, demolding, cooling, shipping for graphitization, exhaust gas/dust collection, exhaust air purification, cranes, filter technology, building equipment (TGA): transformer station, hall ventilation, heating; automation, interlinking