Handtmann - Factory planning HPDC Foundry Kechnec

References
Image
Fabrikplanung Handtmann Kechnec Layout.png
Image
Fabrikplanung Handtmann Kechnec Luftbild.jpg
Image
Fabrikplanung Handtmann Kechnec Luftbild2.p
Image
Fabrikplanung Handtmann Kechnec DGM.png
Image
Fabrikplanung Handtmann Kechnec Anlagen.png
Image
Fabrikplanung Handtmann Kechnec Bearbeitung.png
Image
Fabrikplanung Handtmann Kechnec Anlage.png
Image
Fabrikplanung Handtmann Kechnec Bauteil.png

Video Fa. Handtmann promotional film Kechnec plant Photos: Source: Project engineers or Handtmann promotional film

Background

Albert Handtmann Metallgusswerk GmbH & Co. KG manufactures aluminum and magnesium parts for the automotive industry using die casting or gravity casting processes. Handtmann plans to build a die casting plant for housings and structural components in Kechnec (near Kosice, Slovakia). The new plant will implement state-of-the-art manufacturing concepts and can be expanded in a modular fashion. 

Handtmann commissioned Projektingenieure (PI) with the design and detailing of the new plant.

Result
  • Factory for aluminum die-cast parts put into operation
  • Layout for modular growth and separate truck and personnel traffic 
  • Fully automated, fully interlinked production 
  • Scalable capacities, flexible growth possible in different production areas 
  • Implementation of the highest requirements for occupational safety, environmental protection, and energy efficiency
PI services

Factory planning, process planning, logistics planning

Concept design 
analogous to VDI 5200, phases 1 to 3

  • Capacity requirements, material flows, and logistics areas simulated in scenarios 
  • Production segments defined 
    • Smelting: shaft furnaces 
    • Foundry: fully automatic casting cells for die casting machines up to 35 MN 
    • Blasting: continuous blast system 
    • Mechanical processing: fully interlinked, including machining, high-pressure cleaning, leak testing, etc. 
    • Tool and machine maintenance 
    • Measuring rooms, laboratories 
    • Office and social areas, energy and media supply, 
  • IT networks 
  • Logistics concept (material flow, staging areas, conveyor systems, storage systems) created 
  • Layout start and modular extensions created 
  • Resources (personnel, equipment, buildings, infrastructure) dimensioned 
  • Investments determined 
  • Master plan for implementation created

Detailing 
analog VDI 5200, Phasen 4 und 5

  • Detailed manufacturing segments 
  • Machine layout plan created 
  • Piping and instrumentation diagram (P&ID) for media supply and disposal created 
  • Construction and infrastructure requirements specified (specifications) 
  • Budget and schedule created
Topics

Factory planning: value stream, production segments, material flow, layout, scalability, step-by-step expansion, facilities/infrastructure/buildings, cleanliness, environmental protection 

Process planning: Process engineering, plant engineering, simulation of capacity requirements, automation, interlinking, energy efficiency, IT, control technology, machine and process data acquisition, Industry 4.0

Logistics planning: Simulation of movements/inventories, conveyor technology: Storage technology/transport technology, fire protection

Trades

Charging, melting, dosing, casting, spraying, removing, cooling, deburring, burr disposal, marking, cleaning, blasting, testing, mechanical processing, leak testing, impregnation, packaging, transport, storage; automation, interlinking buildings, pits, foundations, ventilation technology, cranes, media, infrastructure

Handtmann Metallgusswerk GmbH & Co. KG
Factory planning new high pressure die casting (HPDC) foundry
Product
Die-cast aluminum - Gearbox housing
Location
Kechnec, Slovakia
Area of halls:
18.000m²
Project period:
5 months (PI), 2 years total